Regulation 38 Handover

The fire safety information a building's owner needs to run it safely, handed over when the work is finished.

Get a quote

Regulation 38 at completion

Statutory basis
Regulation 38 of the Building Regulations 2010, for new buildings, extensions and changes of use where the Fire Safety Order will apply. Source: Regulation 38, legislation.gov.uk
Point in the project
Once, no later than the date the work is completed or the building is occupied, whichever comes first. Source: Regulation 38, legislation.gov.uk
Document produced
A handover pack for the responsible person: the as-built fire strategy, the drawings, and the information on the fire safety systems they will have to run and maintain. Source: Regulation 38, legislation.gov.uk

In brief

When a new building, an extension or a change of use is finished, the fire safety information has to go to the person who will run the building. It is one of the most often missed steps in a project.

What Regulation 38 asks for

The regulation is short. Where the Fire Safety Order will apply to the finished building, which covers almost everything except a single private house, the person carrying out the work must give fire safety information to the responsible person. That means information about the design and construction of the building and the fire safety services, fittings and equipment in it, enough to let them operate and maintain it with reasonable safety.

It sounds simple. The trouble is timing: by completion the design team has often moved on, the contractor is chasing snagging, and the strategy written at the start no longer matches what was built.

What a good handover pack holds

  • The as-built fire strategy, revised to match what was really built
  • Fire strategy drawings showing compartments, escape routes, fire doors and fire-resisting walls
  • Records of fire-stopping where services pass through compartment walls and floors
  • Commissioning certificates for the alarm, emergency lighting, smoke control and sprinklers
  • A schedule of fire doors with their rating and self-closing devices
  • Details of dry or wet risers, firefighting lifts and fire service access
  • Operating and maintenance information for each fire safety system
  • A note of who received the pack and on what date

Where the fire engineer comes in

A fire engineer revises the strategy to reflect the changes made on site, marks up the as-built drawings, and turns the commissioning records into something the responsible person can follow. On larger projects they also walk the building before handover to check that what the strategy describes is really there: the right doors, closers that work, fire-stopping where the drawings say it is.

If the engineer who wrote the original strategy is still on the project, they are the natural choice. If not, another engineer can take it on, though they'll need to read the strategy and the change history first. The fee depends on how far the as-built building has drifted from the design.

Higher-risk buildings and Gateway 3

For buildings 18 metres or 7 storeys and over with two or more homes, the handover information is part of the golden thread the Building Safety Act requires, and it has to be kept up to date for the life of the building. Before anyone moves in, the client applies to the regulator for a completion certificate. The Gateway 2 page covers the approval before work starts.

A full checklist for the pack is on our rules page, and our article on fire information in the golden thread covers the records for tall buildings.

Handover questions from contractors and owners

Who has to hand over the Regulation 38 information?

The person carrying out the work, which in most projects means the client and its main contractor between them. It goes to whoever holds the Fire Safety Order duties for the finished building, often the owner or its managing agent.

What happens if it is never handed over?

The responsible person is left running a building without knowing how it was meant to work, and the fire risk assessor has nothing to check against. Building control may refuse to issue a completion certificate until it is done. Owners who find the pack missing often commission a retrospective fire strategy to fill the gap.

How does this differ for higher-risk buildings?

For a higher-risk building the same information feeds the golden thread that the Building Safety Act requires, and the client must apply to the regulator for a completion certificate at Gateway 3. The regulator's figures for July to September 2026 show Gateway 3 cases taking months, so start the pack early.

Quotes for a handover pack

Tell us where the building is. The engineer will ask about the original strategy and what changed on site when they call.

We look for one fire engineer suited to the scheme. You'll know who they are before they hear anything about you, and there's no charge from us.

Worth having to hand: the address, the use, the number of storeys and whichever drawings you hold.

The site and how to reach you
Get a quote