Gateway 2 Waiting Times
How long the Building Safety Regulator has really taken to approve work on higher-risk buildings, from its own published figures, release by release.
Approval times against the rule
The guidance gives the regulator 12 weeks to decide on a Gateway 2 application for a new higher-risk building and 8 weeks for work to an existing one. In every release from spring to autumn 2026, the median time to approve a new building sat at 22 or 23 weeks, close to double the statutory period.
Applications to fix external walls on existing blocks took longer still, a median of 32 weeks in the latest release, though that figure has come down from 39 weeks in the March to May 2026 release. Work inside existing buildings sat around 31 weeks.
Approval rates for new buildings rose across the period, from 90% to 97%. More applications are getting through; they are not getting through faster.
Release by release
Each release covers three months. The regulator changed how it grouped applications in spring 2026, so internal works were not split out in the earliest release used here.
| Release | New HRBs in | Decisions | Approved | Median weeks, new | Median weeks, remediation | Median weeks, internal works |
|---|---|---|---|---|---|---|
| March to May 2026 | 64 | 31 | 90% | 22 | 39 | Not split out |
| April to June 2026 | 57 | 37 | 89% | 22 | 35 | 28 |
| May to July 2026 | 53 | 45 | 91% | 22 | 34 | 32 |
| June to August 2026 | 63 | 50 | 92% | 22 | 33 | 32 |
| July to September 2026 | 114 | 57 | 97% | 23 | 32 | 31 |
What it means for a programme
A contractor waiting for Gateway 2 can't start on site, so every week of delay costs money. Three practical points follow from the figures:
- Plan for around six months from submission, not three.
- A strategy written for the specific building, with its drawings, answers queries faster than one adapted from another scheme.
- Settle the design before submitting. Late changes go through change control and can need approval of their own.
Read more on our Gateway 2 fire strategy page, check what a strategy costs, or see the rules behind the gateways.
How we built this
We took the Gateway 2 headline tables from each Building Safety Regulator release on gov.uk, published as transparency data under the Open Government Licence. "Median weeks" is the regulator's median time to approval for applications decided in each three-month window. "New HRBs" means new higher-risk buildings and conversions; in the March to May release the regulator labelled these as its new build unit. The August to October 2026 release was published as a PDF only and is not yet included.
Sources
- Building Safety Regulator building control approval application data (gov.uk collection)
- Release: March to May 2026, published 9 June 2026
- Release: April to June 2026, published 1 July 2026
- Release: May to July 2026, published 12 August 2026
- Release: June to August 2026, published 15 September 2026
- Release: July to September 2026, published 9 October 2026
- Building control approval for higher-risk buildings (gov.uk)
Quotes for a Gateway 2 strategy
Tell us where the site is. An engineer with Gateway 2 experience will call about the scheme and the drawings.
We look for one fire engineer suited to the scheme. You'll know who they are before they hear anything about you, and there's no charge from us.
Worth having to hand: the address, the use, the number of storeys and whichever drawings you hold.
Enquiry received
- An engineer matched to the site and building type is emailed to you by name.
- Reply yes and your details go to them; reply no and the enquiry closes.
- The engineer calls, asks for the drawings and sends a written fee.