What Fire Information Goes Into the Golden Thread

In one paragraph

For higher-risk buildings, the Building Safety Act requires a golden thread of information kept digitally for the building's life. The fire strategy, its drawings and the records of the fire safety systems are at the centre of it, and they have to be kept current, not filed and forgotten.

The golden thread is the name the Building Safety Act 2022 regime gives to the information about a higher-risk building that must be kept, in digital form, from design through to occupation and beyond. Fire information is the largest part of it.

Which buildings it applies to

Higher-risk buildings in England: 18 metres or 7 storeys and over with two or more homes, and hospitals and care homes of that height. For new buildings the thread starts at design and passes from the client to the accountable person when the building is occupied.

The fire information it should hold

From the design and construction stages:

  • The fire strategy as approved at Gateway 2, and each revision after it
  • The fire strategy drawings, updated to the as-built position
  • The reasoning behind any engineered departure from the guidance
  • External wall specifications and product data
  • Fire-stopping and compartmentation records, with photographs where taken
  • Commissioning records for the alarm, sprinklers, smoke control and firefighting lifts
  • The fire door schedule

From occupation onward:

  • Fire risk assessments and the actions taken on them
  • Maintenance and testing records for each fire safety system
  • Changes to the building and their effect on the strategy

How it differs from a Regulation 38 pack

Regulation 38 applies to most new buildings and requires the fire safety information to be handed over at completion. The golden thread goes further for higher-risk buildings: it must be kept up to date, kept digitally, and be available to the people who need it, including the regulator.

In practice a good Regulation 38 pack is the core of the fire part of the golden thread. The difference is what happens next.

Where projects fall down

The usual gap is the strategy itself. It was written for Gateway 2, the design changed during the build, and no one updated it. When the client applies for a completion certificate at Gateway 3, the regulator expects the information to match what was built. An engineer who is kept on through construction can update the fire strategy report as changes happen, which is cheaper than reconstructing it at the end.

If you are planning a tall residential scheme, our Gateway 2 page covers the start of the process, and the Gateway 2 waiting times study shows how long approval takes.

Sources

Fire strategy quotes for your project

Tell us where the site is and how to reach you. An engineer will ask about the building and the drawings when they call.

We look for one fire engineer suited to the scheme. You'll know who they are before they hear anything about you, and there's no charge from us.

Worth having to hand: the address, the use, the number of storeys and whichever drawings you hold.

The site and how to reach you
Get a quote