In one paragraph
Planning Gateway One applies to planning applications in England for buildings 18 metres or 7 storeys and over that contain two or more homes or student rooms. Outline and section 73 applications are exempt. If it applies, the application needs a fire statement and the Building Safety Regulator becomes a consultee.
Planning Gateway One is the first of the three gateways for tall residential buildings in England. It began on 1 August 2021, and it decides whether your planning application needs a fire statement.
The three tests
A scheme is caught when all of these apply:
- It is a planning application in England for a new relevant building, for development of an existing one, or within its curtilage. Outline applications and section 73 applications to vary conditions are exempt. The planning practice guidance lists the others.
- The building is 18 metres or more, or has 7 or more storeys. Both are measured as the guidance sets out.
- It contains two or more dwellings or educational accommodation, such as student rooms.
A mixed-use building with homes on its upper floors counts. A tall office building with no homes does not.
Measuring the height
The planning practice guidance measures height from ground level on the lowest side of the building to the upper floor surface of the top storey, not to the roof. A top storey made up only of roof-top plant is ignored. A storey that is entirely below ground is left out of the count, and a mezzanine counts as a storey if its floor area is at least half that of the largest storey above ground.
If the scheme is near 18 metres or 7 storeys, ask the architect to mark the measurement on a section. Small changes in floor-to-floor height can move a building across the line, with large consequences later at Gateway 2.
What happens if it applies
The application has to be accompanied by a fire statement on the government’s form. The planning authority must then consult the Health and Safety Executive, which does that work through the Building Safety Regulator, before it grants permission. The regulator can comment on the fire safety parts of the scheme, from fire service access to the number of stairs.
The guidance doesn’t name a qualification for whoever completes the form, but a statement from a fire engineer is far less likely to draw questions.
What happens next
A scheme that passes Gateway One will need building control approval from the regulator before work starts, which is Gateway 2. That needs a full fire strategy report, not the statement. Our pages on the planning fire statement and the Gateway 2 fire strategy cover each step, and the rules page puts them side by side.